Shell restarts second stage of hydrocracker at Norco, Louisiana refinery

Royal Dutch Shell Plc began restarting the second stage of the hydrocracker at its 227,400-barrel-per-day (bpd) Norco, Louisiana refinery, sources familiar with plant operations said.

The second stage of the 40,000-bpd hydrocracker was taken out of production on June 8 because of a malfunction, the sources said.

Shell did not reply to a request for comment.

The first stage of the hydrocracker continued to operate while the second stage was shut, according to the sources.