Riley, C.
Targeted liquid injection improves shed deck performance
Process Optimization
/ Project Management
/ Refining
/ Americas
/ Asia/Pacific
/ Distillation
/ Economics
/ Engineering & Design
/ Equipment
/ Europe
/ Heat Transfer
/ Management
/ Middle East
This case study shows how the installation of an unique piping and lance design achieved targeted liquid injection, quenched vapor hot zones and reduced resid entrainment into the heavy coker gasoil product.
- 1
- ... 1 pages
Current Digital Edition
Sign up to Receive Our Newsletter
Latest News
- Sinopec's $4.5-B refinery in Sri Lanka to challenge India's fuel export market share 4/30
- Topsoe secures first SAF project in China 4/30
- Borouge increases Q1 net profit nearly 40% to $273 MM 4/30
- NEXTCHEM finalizes acquisitions of HyDEP and Dragoni to boost green H2 production tech 4/30
- Sponsored Digital Feature: Cut the carbon and boost sustainability 4/30
- Carbon Clean achieves fabrication milestone on FlagshipONE with the project’s first carbon capture unit module 4/30
Construction Boxscore: Project Spotlight
Project:
Long Son Petrochemicals Complex
Location:
Long Son, Vietnam
Operator:
Siam Cement Group
Cost:
$5.4 B
Capacity:
1.65 MMtpy
Completion date:
2023
Status: