Ikegaya, Y.
Yoshihiro Ikegaya is the Product Manager for APC products at Yokogawa. He has developed Yokogawa’s APC products for 15 yr, as well as an additional 6 yr of product planning, marketing and technical support.
Process control reimagined
Maintenance & Reliability
/ Process Control
/ Process Optimization
/ Refining
/ Engineering & Design
/ Environment
/ Equipment
/ Information Systems
/ Loss Prevention
/ Safety
Imagine visiting the control room of a typical process unit at a refinery.
- 1
- ... 1 pages
Current Digital Edition
Sign up to Receive Our Newsletter
Latest News
- Evonik expands distribution partnership with IMCD for VISIOMER® Specialty Methacrylates in the U.S. 3/13
- RWE to invest €17 B in the U.S. to power data centers 3/13
- Petrobras' refineries operating at 97% of capacity 3/13
- ABB open to pursuing more than one multi-billion-dollar acquisition this year 3/13
- USW rejects bp's final offer to Whiting refinery (U.S.) workers 3/13
- Equinor has no spare oil and gas capacity, CEO says 3/13
Construction Boxscore: Project Spotlight
Project:
Long Son Petrochemicals Complex
Location:
Long Son, Vietnam
Operator:
Siam Cement Group
Cost:
$5.4 B
Capacity:
1.65 MMtpy
Completion date:
2023
Status:
Under Construction