In case history, engineers search for root cause of water-side tube failures for a 23-year-old boiler
Flow-induced fatigue failure
Case histories describe a variety of failures and solutions
Failure analysis of above-ground storage tank bottom plates
Here are the field performance assessments and remedial measures
Effect of process deposits on the corrosion behavior of titanium in brine
The temperature and pH need to be controlled to avoid problems
Failure analysis of a primary reformer riser
Investigation revealed the root cause was creep rupture
Top of line corrosion in industrial wastewater pipelines
Here are the causes and the solution
- 1
- ... 1 pages
Current Digital Edition
Sign up to Receive Our Newsletter
Latest News
- KBR's phenol technology selected by SABIC Fujian Petrochemicals 4/25
- Honeywell Technology helping to produce SAF with lower cost and waste 4/25
- Nigeria's NNPC partners local firm on new 100,000 bpd refinery 4/25
- Stranded cargo shows credit challenges at Nigeria's Dangote refinery 4/25
- Low U.S. distillate consumption reflects slow economic activity and biofuel substitution 4/25
- Clariant catalysts reduce customers’ footprints by 40 million tons of CO2e in 2023 4/25
Construction Boxscore: Project Spotlight
Project:
Long Son Petrochemicals Complex
Location:
Long Son, Vietnam
Operator:
Siam Cement Group
Cost:
$5.4 B
Capacity:
1.65 MMtpy
Completion date:
2023
Status:
Under Construction